Whereas in 2011 the continent represented only 4% of our turnover, Jan De Nul substantially strengthened its presence in 2015 and 2016 resulting in a series of beautiful projects. The project in Takoradi opened up other opportunities elsewhere in Africa. In 2016, the company still had six projects going on in the region, part of which are a direct result from the success of the project in Ghana. 

Morocco  

At the end of 2016, Jan De Nul started in Nador, close to the border with Algeria, with the construction of a new port. The first part entails dredging works. The overall project will take four to five years. 

Egypt 

In Abu Qir, to the west of Alexandria, we deepened the military port. 

Ivory Coast 

IIn Abidjan, a site of almost 67 acres was reclaimed for extending the port. 

Nigeria

The Dangote Group – the owner is Africa’s richest man – wants to build its own oil refinery and fertiliser plant in Lekki, 60 kilometres east of Lagos. 

It purchased a site near the coast but this appeared to be too close to sea level to build on. Jan De Nul was engaged to raise the site. We worked continuously from November 2015 to January 2017 with our two largest, world leading hopper dredgers. Just off the coast, at a depth of twenty to fifty metres, we dredged 55 million cubic metres of sand for reclamation.

Congo

After having completed its assignment in Ghana, the cutter suction dredger Ibn Battuta sailed to Pointe Noire for dredging works and for reclaiming a port area of almost 100 acres. It takes about 4 to 5 days to sail from Takoradi to Pointe Noire. 

At a speed of 10-11 knots (about 20 km/h), this corresponds with 400 kilometres per day or a distance of some 2000 kilometres over sea (over land, the distance amounts to 3434 kilometres). 

Mozambique

Africa’s East Coast is featured by a long shallow seabed. Ships that want to visit the port of Maputo must sail in between buoys in a channel of over sixty kilometres. Jan De Nul deployed its cutter suction dredger J.F.J. De Nul from April to December 2016 to deepen the access channel from eleven to fourteen metres. 

After the ports: the coasts

By 2020, many African ports will have been deepened. Maintenance works will always be needed but within a couple of years the extension works will have been completed. Still, West African coasts suffer a great deal from erosion, a process accelerated by climate change. Coasts, roads, houses... are being engulfed by the ocean. With its comprehensive know-how, Jan De Nul can help to protect these vulnerable coasts. 

Related articles

The workshop, a hive of activity

José Pycke already works twenty years for Jan De Nul and is responsible for the workshop in Aalst. The workshop has 70 employees, spread over several departments, almost half are welders but we also have plenty of machine operators, electricians…

Read more
Everyone has much to gain from project financing

A project such as in Takoradi is very capital-intensive. Governments may well have the vision to expand their ports, often their budgets are inadequate. Mathias Van De Vijver, Financial Manager, explains how Jan De Nul can still realise these projects…

Read more
Level foundation under water

The subsoil determines the construction method of a quay wall. In Ghana, it is rocky, which makes it difficult to work with drilled piles. Here, prefabricated concrete blocks offer the best solution. The rock below water acted as foundation after the…

Read more
Concrete in Ghana

For building 600 metres of quay wall, we needed 4,000 concrete blocks or about 100,000 cubic metres of concrete. But Ghana has few concrete batching plants that could reliably meet this demand and quality requirements. That is why Jan De Nul built its…

Read more
Fierce competition

Ignace Stols: “There is fierce competition between West African ports to be chosen as main port by shipping companies. Most of these ports had a depth of 12-13 metre, they are now moving to 15-16 metre. It is a tough race. Only those that are ready…

Read more
Prefabricated concrete block in lego style

The total quay wall height is up to 20.7 metres, with at low tide 3.2 metre above and 17.5 metre below water. It is built of 4,000 concrete blocks each of 50 tonnes, all made on site. When stacking the concrete blocks, these are aligned alternately.…

Read more
Dredging in Winter

Ignace Stols, project manager dredging works, continues: “In November, December and January, the sea in the Gulf of Guinea is less rough. The access channel is situated outside the protected area so we had to be able to make use of this calmer…

Read more
Rock expert from the Ardennes

Takoradi is situated in the Gulf of Guinea. Ordinarily waves are 1.5 metres high, but in stormy weather they are another metre higher. To allow safe and continuous working, we first had to restrain the forces of nature. Pascal Dumez, project manager…

Read more
Thinking along within the framework of the Ghanaian master plan

The project in Takoradi started in 2012; today, it is almost 90% complete. Filip Morobé, Area Director Africa: “What makes this project special, is that there has been no call for tenders. The Ghana Ports and Harbour Authority (GPHA) has…

Read more
Takoradi, Ghana's second largest port

Apart from wood, Takoradi mainly exports cocoa, bauxite and magnesium. The port is also the central pivot for all supplies to Jubilee Field, a huge offshore oil field west of Takoradi. Another part of the cargo entering the port is intended for countries…

Read more